Problem: Beluga was tasked with offloading a hydrocracker weighing 1,306 tons from a barge and bringing it onshore. Due to the weight and 长度 of the hydrocracker utilizing a crane was not an option.
Solution: Beluga utilized two SBL1100 gantry systems to lift the hydrocracker off the barge onto a Self-Propelled Modular Trailer (SPMT). The SPMT then carried the hydrocracker to shore.
Products: Two sets of four SBL1100 Gantries